Cisco Model D-PCG1000 PowerKEY CAS Gateway Installation Guide

Page of 178
 
Chapter 2    Installing the GoQAM 
 
 
 
24 
4004834 Rev D 
Install the Modulator Into a Rack 
The front bezel of the GoQAM mounts to the front of the equipment rack. The 
GoQAM fits into an EIA RS-310 rack mount. 
Important! You must read the preceding section, 
Stacking Guidelines (on page 20)
before installing the modulators into the rack. 
 
Installation Requirements 
This section lists the power, rack, and environmental conditions necessary for 
installation. 
 
Power Requirements Table 
The following table describes the power specifications for the GoQAM. 
Item 
Specification 
Supply Voltage 
 
90V to 130V AC @ 47 to 63 Hz (AC unit) 
 
180V to 264V AC @ 47 to 63 Hz (AC unit) 
 
–42V to –57V DC (DC unit) 
Fuses 
 
4.0 A SLO BLO 250V (AC unit) 
 
6.3 A SLO BLO 250V (DC unit) 
Line Frequency 
 
47 Hz to 63 Hz (AC unit only) 
Power Required 
 
RF GoQAM: 155 VA (typical) 
 
IF GoQAM: 85 VA (typical) 
Power Dissipated 
 
RF GoQAM: 151 Watts (typical) 
 
IF GoQAM: 81 VA (typical) 
In Rush Current 
 
35 amps maximum, Vin = 130V AC (AC unit) 
 
75 amps maximum, Vin = 264V AC (AC unit) 
 
15 amps maximum, Vin = -57V DC (DC unit)