System Integrity Tests
The remaining tests are performed to ensure proper functionality of all system 
components when the ICM is running in duplex mode. Give special attention to 
redundancy testing.
Process testing
Validate processes on the ICM system. For example, check the following 
processes for:
RTR - all configuration data transferred from logger
LGR - completed initialization
AW - updateAW has completed update and waiting work
Step 1
Ensure each software process is running according to specification.
Step 2
Check each NIC for the proper connection to the carrier (IXC) network.
Step 3
Halt and restart each process.
Redundancy testing
Step 1
Stop each active PG to ensure that the back-up PG assumes an active state.
Step 2
Stop the active CallRouter side to ensure that the system switches to the alternate 
CallRouter side without loss of functionality.
Step 3
Perform the same tests on the logger and the NIC.
Alarm testing
Step 1
Verify your Network Operations Center (responsible for Alarm Tracker 
monitoring of the system) is receiving the alarms in their tracking system.