Chapter 2      Preparing for Installation
  Site Preparation Checklist
Also be aware of the following caution concerning the use of Category 5e and Category 6 Ethernet 
cables:
Caution
Category 5e and Category 6 cables can store large levels of static electricity because of the dielectric 
properties of the materials used in their construction. Always ground the cables (especially in new cable 
runs) to a suitable and safe earth ground before connecting them to the module.
Site Preparation Checklist
 lists the site planning activities that you should perform prior to installing the Catalyst 6500 
series switch. Completing each activity helps ensure a successful switch installation.
Table 2-4
Site Planning Checklist
Task No.
Planning Activity 
Verified By Time
Date
1
Space evaluation:
Space and layout
Floor covering
Impact and vibration
Lighting
Maintenance access
2
Environmental evaluation:
Ambient temperature
Humidity
Altitude
Atmospheric contamination
Airflow
3
Power evaluation:
Input power type
Power receptacles (Depends on power supply)
1
Receptacle proximity to the equipment
Dedicated (separate) circuits for redundant 
power supplies
UPS for power failures
DC systems: Proper gauge wire and lugs
4
Grounding evaluation:
Circuit breaker size
CO ground (AC- and DC-powered systems)