 Figure 4 - 11.  Meters Deployed by Day
Installation Status
The Installation Status Report is intended to be used by utilities during mass deployment. It can be 
used as an installation tool to determine how many meter modules have been installed over a speci-
fied time frame and, of those meter modules, how many:
have been discovered.
have moved to normal status.
are sending readings.
have sent readings in the past 24 hours.
Some of the data required for the Installation Status Report is provided via the Import Installation 
file.
Following is the procedure for viewing the Installation Status report:
1. Click Network > Installation Status. The Installation Status window will open.
2. Selection Criteria. Select All to view results for all collectors in the system.
...or...
Select the desired collector from the drop down box to view results for only that collector or 
select All to see all collectors/endpoints in the system.
3. Date Range. Enter a Start Date and End Date. Click the Calendar icon to view a calendar and 
make date selections, if needed.