RadioFrame Networks Inc DH2 User Manual
Method of Procedure
Equipment Commissioning
Equipment Commissioning
94
RFN_3.1 Beta
5.5.2.1 Grounding
Record the following grounding information. For any unacceptable item, take
corrective action and record what occurred, or record the item for the next site
visit.
corrective action and record what occurred, or record the item for the next site
visit.
Yes
No
Buss Bar O.K. (optional)
NCU/ACU rack(s)
Rectifier rack
Battery shelf (GNB)
5.5.2.2 Power
Plant
Measure and record the following voltages for the Peco II rectifier. (For further
information, refer to the product specification information provided by Peco II,
Inc., the rectifier manufacturer: Small DC Power Systems, Spec. No. 127NHL.)
information, refer to the product specification information provided by Peco II,
Inc., the rectifier manufacturer: Small DC Power Systems, Spec. No. 127NHL.)
GNB
Dynasty
Float voltage
Suggested
-54.0 vdc
-54.8 vdc
Measured at
Equalize voltage
Suggested
-56.4 vdc
-58.4 vdc
Measured at
High voltage
Suggested
-56.0 vdc
-58.0 vdc
Measured at
Low voltage
Suggested
-43.0 vdc
-43.0 vdc
Measured at
Low voltage Pick-up
Suggested
-46.0 vdc
-46.0 vdc
Measured at
Low voltage drop-out
Suggested
-42.0 vdc
-42.0 vdc
Measured at
5.5.2.3 Battery
Record the following information for each of the eight batteries.
Plant
Voltage
Measured
At
Connections
Corroded (Y/N)
Terminals
Greased (Y/N)
Signs of
Leakage (Y/N)
Battery 1
Battery 2
Battery 3
Battery 4
Battery 5
Battery 6
Battery 7
Battery 8