RadioFrame Networks Inc DH2 User Manual

Page of 164
Method of Procedure 
Equipment Commissioning 
94 
RFN_3.1 Beta
 
5.5.2.1 Grounding 
Record the following grounding information. For any unacceptable item, take 
corrective action and record what occurred, or record the item for the next site 
visit. 
 
Yes 
No 
Buss Bar O.K. (optional) 
 
 
NCU/ACU rack(s) 
 
 
Rectifier rack 
 
 
Battery shelf (GNB) 
 
 
5.5.2.2 Power 
Plant 
Measure and record the following voltages for the Peco II rectifier. (For further 
information, refer to the product specification information provided by Peco II, 
Inc., the rectifier manufacturer: Small DC Power Systems, Spec. No. 127NHL.) 
 
 
GNB 
Dynasty 
 
 
Float voltage 
Suggested 
-54.0 vdc 
-54.8 vdc 
Measured at 
 
Equalize voltage 
Suggested 
-56.4 vdc 
-58.4 vdc 
Measured at 
 
High voltage 
Suggested 
-56.0 vdc 
-58.0 vdc 
Measured at 
 
Low voltage 
Suggested 
-43.0 vdc 
-43.0 vdc 
Measured at 
 
Low voltage Pick-up 
Suggested 
-46.0 vdc 
-46.0 vdc 
Measured at 
 
Low voltage drop-out 
Suggested 
-42.0 vdc 
-42.0 vdc 
Measured at 
 
5.5.2.3 Battery 
Record the following information for each of the eight batteries. 
 
Plant 
Voltage 
Measured 
At 
Connections 
Corroded (Y/N) 
Terminals 
Greased (Y/N) 
Signs of 
Leakage (Y/N) 
Battery 1 
 
 
 
 
 
Battery 2 
 
 
 
 
 
Battery 3 
 
 
 
 
 
Battery 4 
 
 
 
 
 
Battery 5 
 
 
 
 
 
Battery 6 
 
 
 
 
 
Battery 7 
 
 
 
 
 
Battery 8