Lift and handle the product carefully,  
using suitable lifting equipment. Observe all 
the accident prevention regulations.
When you receive the pump, check the outside of 
the package for evident signs of damage. If the prod-
uct bears visible signs of damage, notify our distribu-
tor within 8 days from the delivery date.
2. STORING THE PACKED PRODUCT
Ambient temperature 3º F to 104º F.
Short Term: (Less than 6 months) Goulds Pumps 
normal packaging procedure is designed to protect 
the pump during shipping. Upon receipt, store in a 
covered and dry location.
Long Term: (More than 6 months) Rotate shaft 
several times every 3 months. Refer to driver and 
coupling manufacturers for their long term storage 
procedures. Store in a covered dry location.
3. UNPACKING THE PRODUCT
Use suitable equipment. Observe all the 
accident prevention regulations in force. Lift 
and handle the product carefully, using suit-
able lifting equipment.
When you receive the pump, check the outside of 
the package for evident signs of damage. If the prod-
uct bears visible signs of damage, notify our distribu-
tor within 8 days from the delivery date.
4. HANDLING THE PRODUCT
Lift and handle the product carefully, using 
suitable lifting equipment. Observe the  
accident prevention regulations in force.
The product must be securely harnessed 
for lifting and handling. Some electric pumps have 
eyebolts that can be used for this purpose.
The installation operations must be carried 
out by qualified and experienced personnel. 
Use suitable equipment and protections. 
Observe the accident prevention regulations in force.
Always refer to the local and/or national regulations, 
legislation and codes in force relating to the selec-
tion of the installation site and the water and power 
connections.
1. SITE SELECTION
Make sure that no obstructions or obstacles hinder 
the normal flow of the cooling air delivered by the 
motor fan. Make sure there is adequate clearance 
around the pump for the maintenance operations. 
Whenever possible, raise the pump slightly from 
the level of the floor. See the figures below and at 
the top of the next column for possible installation 
configurations.
2. ANCHORING
The pump must be anchored securely with bolts to 
a concrete foundation or equivalent metal structure 
(shelf or platform). If the pump is large-sized and 
needs to be installed near rooms inhabited by people, 
suitable vibration-damping supports should be pro-
vided to prevent the transmission of the vibrations 
from the pump to the reinforced concrete structure. 
The dimensions of the pump base and anchoring 
holes are shown.
 
1SV  2SV  3SV  4SV  33SV  46SV  66SV  92SV
Inches (mm)
 L1  3.94 (100)  5.12 (130)  6.69 (170)    7.48 (190)
 L2  7.09 (180)  8.46 (215)  9.44 (240)    10.44 (265)
 L3  5.91 (150)  7.48 (190)  8.66 (220)    9.44 (240)
 L4
9.65 (245)  11.42 (290)    12.4 (315)
 Ø A
0.50 (13)
0.60 (15)
 N
4
3. ANGULAR ALIGNMENT
Angular alignment of the suction and discharge 
flanges can best be accomplished using calipers at the 
bolt locations. See figure below.
NOTICE: DO NOT DRAW PIPING INTO PLACE BY 
FORCING THE PUMP SUCTION OR DIS-
CHARGE CONNECTIONS.