7 OPERATION 
 
 
 
 
This symbol refers to the operations of a parallel system. 
 
 
 
 
Verify for correct input/output cabling before connecting Utility 
to the UPS. 
Open only the front door, do not remove any panels. 
 
Now you can initiate the start-up procedure of the UPS system. 
There is no need for specific knowledge if you follow carefully 
the step-by-step instructions given below. 
But we recommend, that at least the initial procedure, should be 
performed by an instructed person. 
 
Check after every step for correct reaction of the UPS (LED’s on 
the panel), and correct voltage and current measurements, 
before you proceed to the next step. 
 
If you encounter any problems during the following procedures, 
you should not continue, but contact GE Global Services
.
 
 
 
 
Find on the following pages the descriptions of the various procedures of 
startup and shutdown for single and parallel UPS’s
divided into the following 
principal chapters:
 
 
7.1 
PROCEDURES FOR SINGLE UPS 
 
 
7.2 
PROCEDURES FOR UPS FUNCTIONING AS FREQUENCY CONVERTER 
 
 
7.3 
PROCEDURES FOR PARALLEL SYSTEM 
 
 
7.4 
PROCEDURES FOR PARALLEL SYSTEM WITH COMMON BATTERY