7.1.3  From Manual Bypass (Q2) to normal function On-line 
 
Initial status: 
Load supplied from Manual Bypass.
 
 
 
 
1.  Close Q1 (Pos. I)
• 
Bypass connects to Load
LED Load on Bypass lights up. 
• 
Rectifier starts automatically and 
LED in Rectifier symbol and LED 
Battery
 charge light up. 
 
 
 
2.  Open Q2 (Pos. O). 
• 
LED Manual Bypass turns OFF. 
 
 
 
3.  Connect the Battery to the UPS by closing the Battery Switch or Fuses, in 
case of External Battery .
 
 
 
4.  Press inverter on ( I ) key. 
• 
Soft-start of Inverter, indicated with 
blinking LED
• 
At the end of Soft-start the LED 
remains lit. 
• 
Automatic transfer from Bypass to 
Inverter
• 
UPS output LED indicates Load on 
Inverter
 
The LCD must display on the main screen the status LOAD ON INVERTER
 
 
End of procedure