This appendix addresses many aspects of installing optical fiber cabling to 
support the CoreBuilder
®
 7000 family ATM switch environment. It also 
deals with modem cables and Ethernet and control cables for 
management. The following topics are covered:
Installing New 
Cabling
If you are installing new cabling, follow these guidelines:
3Com recommends that you use a cabling system plan, such as 
AT&T's Premises Distribution System (PDS) or the IBM Cabling System.
Determine how many CoreBuilder 7000 units are going to be 
supported by each wiring closet, and how many downlink 
connections from these CoreBuilder 7000 units are planned.
Locate wiring closets to enable connections to the different floors. 
To simplify installation of the network and to aid in troubleshooting, 
install a telephone in each wiring closet for communication between 
wiring closets, work areas, and other locations.
Include all linear distances (vertical rises, etc.) in the cable plan so that 
all cables - from wiring closet to desk and to other wiring closets - are 
under their respective maximum lengths.
Cable Labeling and
Record Keeping
A reliable cable labelling and record keeping system is essential when 
planning any network installation. A good cable labelling system provides 
enough information for you to locate the opposite end of any cable. 
Maintaining accurate records helps you to: 
relocate devices easily