U-Line BI2015 Manual De Usuario

Descargar
Página de 17
BI2015 — Ice Maker
02/2005
13
www.U-LineService.com
CAUTION
Plumbing installation must observe all state and local 
codes. All water connections MUST BE made by a licensed/
qualified plumbing contractor. Failure to follow 
recommendations and instructions may result in damage 
and/or harm.
WARNING
To prevent accidental electrocution, make certain 
that the floor surfaces surrounding the unit are 
dry whenever power is removed from, or applied 
to, the unit.
Water Supply Connection
When connecting the water supply, follow these 
guidelines:
• Review the local plumbing codes before you install the 
unit.
• Connect to the cold water supply.
• The water pressure should be between 20 and 120 psi.
• Install a shut-off valve in the 1/4 inch OD water supply 
line.
• Connect sufficient tubing to the unit so that tubing 
may be looped, allowing the unit to be removed for 
cleaning and servicing (see Figure 32). However, make 
certain that the tubing is not pinched or damaged 
during installation.
• U-Line recommends the use of copper tubing for 
installation.
To connect to water supply:
1. Install the 1/4 inch OD copper water line from the 
main water source (see Figure 30).
2. Locate the compression fitting and ferrule packed with 
the unit. Slide the compression fitting and ferrule over 
the 1/4-inch OD water supply line. Do not use thread 
sealing compound or tape. Using two wrenches, 
tighten the compression fitting on the supply line 
(see Figure 31).
3. Carefully bend the water 
supply line into position 
and connect the line to 
the solenoid valve (see 
Figure 32). Avoid kinking 
the water supply line.
IMPORTANT
Normal operation creates some vibration. A water supply 
line contacting cabinet wall may cause excessive noise 
during operation or damage to the line.
4. For recessed installations, allow extra water supply line 
length to provide slack for easy removal from the 
recessed area (see Figure 32). This will also safeguard 
against kinking the line. 
5. Go on to 7 Prepare Power Supply.
6 Prepare  Plumbing
Figure 31
Figure 30
Water
Connection
Figure 32