Empire Comfort Systems DVP48FP9 Manuel D’Utilisation

Page de 52
Page 23
17375-6-0705
Installing Support Brackets (Figure 37)
A  horizontal  pipe  support  MUST  BE  used  for  each  3  feet  of 
horizontal run. The pipe supports should be placed around the  
pipe and nailed in place to framing members. There MUST BE 
a 3 inch clearance to combustibles above 8 inch diameter pipe 
and elbows and 1 inch clearance on both sides and bottom of the 
8 inch dia. pipe to combustibles on all horizontal pipe sections 
and elbows. 
Vertical runs of this vent systems must be supported every 4 feet 
above the appliance flue outlet by wall brackets attached to the 
8 inch vent pipe and secured with nails or screws to structural 
framing members.
 
Figure 37
Installing Firestops (Figures 38, 39, 40 and 41)
Firestops are required for safety whenever the vent system passes 
through  an  interior  wall,  an  exterior  wall,  or  a  ceiling.  These 
firestops act as a firebreak heat shield and as a means to insure that 
minimum clearances are maintained to the vent system.
Horizontal  runs  in  the  vent  system  which  pass  through  either 
interior or exterior walls, require the use of wall firestops on both 
sides of the wall through which the vent passes.
Cut a 10-3/8 inch x 12-3/8 inch hole in wall. Position firestop 
(SD1249) on interior side of wall for 10-3/8 inch x 12-3/8 inch 
hole.
Attention: Wall firestop hole is off-set towards bottom of wall 
opening. Secure with nails or screws. Continue the vent run through 
the firestop (See Figure 38).
FRAMING AND FINISHING
10 3/8
12 3/8
WALL FIRESTOP
HOLE IS OFF-SET
TOWARDS BOTTOM
OF WALL OPENING.
Figure 38
Vertical runs of this system which pass through ceilings require the 
use of ONE (1) ceiling firestop at the hole in each ceiling through 
which the vent passes.
Position a plumb bob directly over the center of the vertical vent 
component and mark the ceiling to establish the center point of the 
vent. Drill a hole or drive a nail through this center point and check 
the floor above for any obstructions such as wiring or plumbing 
runs. Reposition the appliance and vent system, if necessary, to 
accommodate ceiling joists and/or obstructions.
Cut a 10 1/2 inch x 10 1/2 inch hole through the ceiling, using 
the center point previously marked. Frame the hole with framing 
lumber the same size as the ceiling joists. (See Figure 39) If the 
area above the ceiling is NOT an attic, position and secure the 
ceiling firestop (SD-1263) on the ceiling side of the previously cut 
and framed hole. (See Figure 40) If the area above the ceiling is 
an attic, position and secure the firestop on top of the previously 
framed hole. (See Figure 41)
NOTE: Remove insulation from the framed area in the attic before 
installing the firestop and/or vent pipes.