Huawei Technologies Co. Ltd BTS3812A-1900 Manuel D’Utilisation
NodeB LMT User Guide
Chapter 9 Monitoring NodeB Performance and State in
Real Time
Huawei Technologies Proprietary
9-13
4) Click
OK.
A monitor window is displayed showing the service resource occupancy curve.
5) Stop the test in either way below:
z
Close the monitor window.
z
Right-click the task in the task list below the graphical area. Click Delete Task on
the shortcut menu to delete the task and curve.
the shortcut menu to delete the task and curve.
IV. Test Result Analysis
Once the test is started, the system reports the output power of the MTRU and each
carrier every two seconds.
carrier every two seconds.
9.9 Testing MTRU Temperature
I. Introduction
The MTRU temperature test measures the temperatures of the MTRU board and the
internal power amplifier.
internal power amplifier.
II. Prerequisite
None.
III. Procedure
Follow the steps below to test the MTRU temperature:
1) Choose
Maintenance Navigator -> Realtime State Monitoring. Right-click on
the MTRU Temperature subnode.
2) Click
Create Monitor Task.
The system displays the MTRU Temperature dialog box, as shown in Figure 9-7.
Figure 9-7 MTRU Temperature dialog box
Table 9-7 describes the fields of the MTRU Temperature dialog box.