3.6.2  Connect GPS Antenna 
1.  Insert GPS jumper into cold shrink tube. 
2.  Connect one end of the GPS jumper to the GPS antenna.   
3.  Push the cold shrink tube to the top joint and pull out the strip. 
4. 
Connect  the  other  end  of  the  GPS  jumper  to  GPS  interface  of  the  base  station, 
which also need weatherproof protection.
 
3.6.3  Connect RF Cable 
1.  Open the dust cap of ANT0 and ANT1 interface. 
2.  Insert RF cables into cold shrink tube. 
3.  Connect  one  end  of  the  two  RF  cables  to  ANT0  and  ANT1  interface  of  the  base 
station and tighten them with wrench. 
4.  Push the cold shrink tube to the top joint and pull out the strip. 
5.  Connect the  other  end  of the RF cables to the  external antenna, which also need 
weatherproof protection. 
3.6.4  Connect Ethernet Cable 
1.  Connect the Ethernet cable to ETH0 interface in the wiring cavity. 
2.  Lay  Ethernet  cable  along  the  wire  groove,  and  stretch  out  the  wiring  cavity  from 
ETH0 hole. 
3.6.5  Connect Power Connector 
Because  it  is  not  sure  that  the  distance  between  the  installation  site  and  the  power 
supply device, the two ends of power adapter are bare terminal end. The operators need 
to make power cable according to the actual conditions on installation site, and assemble 
power plug and power terminal on two ends of power adapter. 
Strip 12mm insulating layer with wire stripper, which is used for connection to connector. 
It is recommended that the power cord length is kept below 100m (330 feet). 
The connection steps of power cable is as follows.   
1.  Assemble power plug. 
The  power  plug  will  be  installed  on  the  end  of  input  direction.  Refer  to  the 
identification  on  power  plug,  connect  live  wire,  neutral  wire,  and  ground  wire  to