Nova-243 Outdoor LTE TDD Base Station Installation Guide 
13 
 
 
4.  Drill  three  12mm  diameter  holes  in  the  wall  on  the  marked  locations,  and 
insert the expansion pipes. 
5.  Fix base station to the wall with M8 x 80 expansion bolts.   
 
Connect Cable 
3.6
3.6.1  Requirement for Cable Laying 
General requirements: 
 
Bending radius requirement of feeder cable: 7/8
” > 250mm, 4/5” > 380mm.   
 
Bending radius requirement of jumper cable: 1/
4” > 35mm,1/2” (super soft) > 50mm,
1/2
” (ordinary)>127mm. 
 
Bending  radius  requirement  of  power  cable  and  grounding  cable:  >  tripled  of  the 
diameter of cable. 
 
Binding the cables according the type of the cable, the intertwining and crossing is 
forbidden. 
 
The label should be paste after the cable laying. 
Grounding laying requirement: 
 
The grounding cable must connect to the grounding point. 
 
The grounding cable must be  separate with the signal cables, remaining a certain 
distance to avoid the interruption of signal.