CALL SERVICEMAN
SERVICE AND MAINTENANCE SUGGESTIONS
GENERAL:  All furnaces have been fire-tested to check for proper 
operation.  This includes, main burner flame, pilot flame, fan operation, 
fan control, limit control and automatic valve operation.  If the furnace 
fails to function on initial installation, it is advisable to re-check the 
following: 
1.  115 volts to the junction box.
2.  Inlet gas pressure.
3.  The 24 volt system.
4.  Type of gas being used and that shown on the rating label.
The Service Department at Empire Comfort Systems, Inc. may be 
contacted to assist in servicing furnace.
Servicing the Pilot and Main Burners, Pilot Orifice, and Main 
Burner Orifices:  Disconnect the gas supply at the inlet to the control 
valve.  Then remove the burner door to which the above components 
are attached.
Servicing  The  Fan  Motor:    The  upper  front  panel,  the  shroud 
surrounding the fan blade and fan blade must be removed.  See “Oiling 
the Motor” paragraph on page 7.
S 8 6 0 0 H   I N T E R M I T T E N T  I G N I T I O N   M O D U L E 
SPECIFICATIONS
Lockout timing is 90 seconds.  Ignition timing is until pilot lights or 
lockout occurs.
Module shuts down and cuts power to gas control on flame failure.  
Gas control closes to provide 100 percent lockout on flame failure.  
Manual reset required.
ELECTRICAL RATINGS:
Voltage and frequency:  20.5 to 28.5V (24V nom.) 60 Hz.
Current rating:  0.2 A.
Valve contact ratings (at 24 Vac):
 
 
Run 
Inrush
 
Pilot   1.0 A 
10.0 A
 
Main  1.0 A 
10.0 A
SPARK GENERATOR OUTPUT:  13kV peak at 25 pf load.
THERMOSTAT ANTICIPATOR SETTING:  0.2 A plus pilot valve 
rating plus main valve rating.  
THERMOSTAT COMPATIBILITY:  Standard models compatible with 
all open-close switch type 24 Vac thermostats capable of supplying 
rated voltage and current to the module.
AMBIENT TEMPERATURE RATING:  Minus 40 F to plus 175 F 
(minus 40 C to plus 79 C).
RELATIVE HUMIDITY RATING:  5 to 90 percent RH at 95 F.
FLAME FAILURE RESPONSE TIME:  0.8 seconds at 1.0 uA flame 
current.
FLAME CURRENT:  1 uA, min.
CHECKOUT
Check out the gas control system:
  1.  At initial installation of the appliance.
  2.  As part of regular maintenance procedures.
  3.  As the first step in troubleshooting.
  4.  Any time work is done on the system.
STEP 1:  Perform Visual Inspection.
  A.  With power off, make sure all wiring connections are clean and 
tight.
  B.  Turn on power to appliance and ignition module.
  C.  Open manual shutoff valves in the gas line to the appliance.
  D.  Do  gas  leak  test  ahead  of  gas  control  if  piping  has  been 
disturbed.
    GAS LEAK TEST:  Paint pipe joints with rich soap and water 
solution.  Bubbles indicate gas leak.  Tighten joints to stop leak.
STEP  2:    Review  Normal  Operating  Sequence  and  Module 
Specifications.
STEP 3:  Reset the Module.
  A.  Turn the thermostat to its lowest setting.
  B.  Wait one minute.
    As  you  do  Steps  4  and  5,  watch  for  points  where  operation 
deviates from normal.  Refer to Troubleshooting Chart to correct 
problem.
STEP 4:  Check Safety Lockout Operation.
  A.  Turn gas supply off.
  B.  Set thermostat above room temperature to call for heat.
  C.  Watch for spark at pilot burner.   
  D.  Time  length  of  spark  operation.    Maximum  spark  time  is  90 
seconds.
  E.  Open manual gas cock and make sure no gas is flowing to pilot 
or main burner.
  F.  Set  thermostat  below  room  temperature  and  wait  one  minute 
before continuing.
STEP 5:  Check Normal Operation.
  A.  Set thermostat above room temperature to call for heat.  
  B.  Make  sure  pilot  lights  smoothly  when  gas  reaches  the  pilot 
burner.
  C.  Make sure main burner lights smoothly without flashback.  Make 
sure burner operates smoothly without floating or lifting.
  D.  If gas line has been disturbed, complete gas leak test.
    GAS LEAK TEST:  Paint gas control gasket edges and all pipe 
connections downstream of gas control, including pilot tubing 
connections, with rich soap and water solution.  Bubbles indicate 
gas leaks.  Tighten joints and screws or replace component to stop 
gas leak.
  E.  Turn thermostat below room temperature.  Make sure main burner 
and pilot flames go out.
OPERATION
Module  operation  can  be  conveniently  divided  into  two  phases 
for  S8600H.    The  phases  are  trial    for  ignition  and  main  burner 
operation.
TRIAL FOR IGNITION
Pilot Ignition
Following call for heat (system start on S8600H), the module energizes 
the first main valve operator.  The first main valve opens, which allows 
gas to flow to the pilot burner.  At the same time, the electronic spark 
generator in the module produces a 13,000 volt spark pulse output (at 
25 pf load).  The voltage generates a spark at the igniter-sensor that 
lights the pilot.