Lifting Guidelines 
The SV Director Server weighs between 30 lb (13.6 kg) and 51.5 lb (23.4 kg) 
depending on what hardware options are installed in the server. The server is not 
intended to be moved frequently. Before you install the server, ensure that your 
site is properly prepared so you can avoid having to move the server later to 
accommodate power sources and network connections. 
Whenever you lift the server or any heavy object, follow these guidelines: 
  Always disconnect all external cables before lifting or moving the server. 
  Ensure that your footing is solid, and balance the weight of the object 
between your feet. 
  Lift the server slowly; never move suddenly or twist your body as you lift. 
  Keep your back straight and lift with your legs, not your back. If you must 
bend down to lift the server, bend at the knees, not at the waist, to reduce the 
strain on your lower back muscles. 
  Lift the server from the bottom and grasp the underside of the server exterior 
with both hands. 
Site Preparation 
Warning! This unit is intended for installation in restricted access areas. A 
restricted access area can be accessed only through the use of a special tool, 
lock and key or other means of security. Statement 1017 
Typically, you should have prepared the installation site beforehand. As part of 
your preparation, obtain a floor plan of the site and the equipment rack where the 
SV Director Server will be housed. Determine the location of any existing 
appliances and their interconnections, including communications and power. 
Following the airflow guidelines to ensure that adequate cooling air is provided to 
the server. See 
. 
All personnel involved in the installation of the server including installers, 
engineers, and supervisors should participate in the preparation of a MOP for 
approval by the customer. See 
. 
The following sections provide the site preparation requirements that you must 
consider before installing the server: 
 
 
 
 
 
 
Rack Mounting 
The SV Director Server should be installed in a 4-post equipment rack that 
complies with the Electronics Industries Association (EIA) standard for 
equipment racks (EIA-310-D). Figure 13 shows a free-standing, 4-post open rack