Chapter 8 Installing Main Antenna Feeder System
ii. According to the installation drawing of antenna and feeder
in the engineering design drawing, confirm the installation
position of antenna rack.
iii. Extend the rack out of the iron platform and fasten it on
the tower body with U-shape fixation clips (connection bar
and U-shape bolt included), as shown in
F
IGURE
104 A
NTENNA
R
ACK
I
NSTALLATION
1.
Connection bar
2.
U-shape bolt
3.
Iron platform
iv. Connect guard bars of platform and connect bottom plates.
If it is inconvenient to connect the antenna rack with the
guard bars, weld them and make sure welding fastened.
Cover a layer of antirust paint on the all parts welded and
on the surface of rack.
2. Installing the omnidirectional antenna
i.
According to the engineering design drawing, make sure
the installation direction of antenna.
ii. Fix the antenna on the fixation mast of rack, as shown in