Check whether the
PE
wire pole of ground cable is proper and
firm.
Internal Cable
Inspection
Check the internal cables as follows, and make sure:
The internal cable of rack is hung in the air.
The RF cable of the front panel, clock cable, power and alarm
cable as well as test cable are connected well and properly.
The cable layout route and binding space are reasonable and
correct.
Layout of the fiber bellows inside the rack is beautiful and rea-
sonable.
The protective ground cable of rack door is connected well,
avoiding lack and looseness phenomena.
The cable surface is clean without any engineering mark and
the sheath insulation layer is undamaged.
Socket, Plug and Locking Piece
Inspection Items
The socket, plug and locking piece inspection items include:
Check whether connection of the socket, plug and locking piece
is proper, avoiding misconnection and leaking connection.
Check whether connection between plug and socket is fas-
tened. The fastness screw on the boards should be screwed
down, and the locator card should be put in proper position
without any damage.
Check whether the plug made on site does not damage the
core cable.
Check whether the cable plug and licking piece are fastened.
Make sure no bin-lacked or bin bent-phenomenon occurring in
the socket and plug.
Label Inspection Items
Label inspection items include:
Check whether the label adopts a special adhesive paper for
ZTE.
Check whether the directions of affixed labels are consistent.
To be convenient for reading, a side of label that indicates ca-
ble orientation should be placed upwards or towards a main-
tenance and operation side.
Check whether label content of rack row and rack line accords
with the requirements of engineering design. All ZTE devices
in the equipment room should be distributed in order.
148