Chapter 9 Installation Check
Check whether circuit breakers of power cable are affixed in a
power cabinet and power distribution cabinet in order .
Check whether circuit breakers of power cable in a power cab-
inet and power distribution cabinet indicate connection orien-
tation with a label.
Check whether labels are affixed to both ends of all cables
(ground cable, transmission cable and jumper, except protec-
tive ground cables of cabinet door and side door). Make sure
handwriting clear on the labels and label positions consistent.
If a label is required to cling to a board, make sure handwriting
clear and affixed label positions orderly.
On-site Environment Inspection Items
On-site environment inspection items include:
Check whether redundant sundries left inside the cabinet, as
well as the front, back and side door are clean. After cabinet
installation completion, clean up the cabinet surfaces inside
and outside.
Check whether redundant goods in the equipment room is
cleared out as well as the operation platform and floor are
clean and in order. Make sure goods in the equipment room
orderly.
Check whether the cable tray, cabinet bottom and floor round
the cabinet are clean up. Make sure all cables in order.
Checking Antenna Feeder
System Installation
Checking Feeder
Prerequisite
Install the GPS antenna feeder system.
Steps
1. Make sure the hung height of antenna consistent with network
planning.
2. Make sure the installation position of antenna in accordance
with the design drawing.
3. Make sure that connection between antenna rack and iron
tower is fastened.
4. Make sure the antenna position within a protective area of ar-
rester.
5. Make sure clamping nuts screwed down and spring washes
pressed levelly.