Chapter 4 Operation and Maintenance
Table 4-3 Power-on Steps
Item
Power-on Steps
DC power
supply
1.
Turn on the switch of the power distribution unit, and check whether the equipment
output voltage is in the normal range.
2.
Turn on the switch of the indoor DC power lighting protection box of the ZXSDR
R8978. Power the ZXSDR R8978 on, and test whether the
RRU
input voltage
is in the normal range.
3.
Check whether the
BBU
indicator or the
RRU
indicator is normal.
AC power
supply
1.
Turn on the switch of the AC power distribution unit of the ZXSDR R8978, and
check whether the equipment output voltage is in the normal range.
2.
Check whether the
BBU
indicator or the
RRU
indicator is normal.
Note:
To avoid current surge, you need to power on the
RRU
s in the cell sequence every 30
s. At the same time, you can check whether the cables of a cell are connected properly
through the
BBU
indicator.
4.5 Power Off
Power-off of the ZXSDR R8978 includes:
l
Emergency power-off: occurs when the equipment room is on fire, flooding or in smog.
l
Common power-off: occurs in some application scenarios, for example, equipment
move or expected local power outage.
For a description of the ZXSDR R8978 power-off flow, refer to
.
Table 4-4 Power-off Steps
Item
Emergency Power-off
Common Power-off
DC power supply
Turn off the air switch
of the indoor DC power
distribution unit.
1.
Turn off the air switch of the DC power
lighting protection box of the ZXSDR
R8978.
2.
Turn off the air switch of the indoor DC
power distribution unit.
AC power supply
Turn off the air switch of the indoor AC power distribution unit.