ZTE Corporation RSU82C Manuale Utente

Pagina di 55
Chapter 5 Hardware Installation
Steps
1.
Affix temporary labels to both ends of the SFR cable, with markings 0-5 to set up
one-to-one mapping with interfaces TX0RX0 to TX5RX5 of BBU and six TX/RX
interfaces of RSU.
2.
Insert one end of the SFP cable to a TX/RX interface of RSU.
3.
Route the SFP cable along the routing trough and cabinet sides to the FS module of
BBU. The SFP cables connecting to the RSUs in slots 1 to 3 on the RF cabinet go
through the left routing apertures and those SFP cables go through the right apertures
if connecting to slots 4 to 6 on the RF cabinet, as shown in
and
.
Figure 5-13 Layout of the SFP Cables in the RF Cabinet
5-13
SJ-20101019140047-001(R1.2)|08/08/2011
ZTE Proprietary and Confidential