Carton Unpacking Procedure 
1.  Cut the straps by using the diagonal pliers;  
2.  Cut the adhesive tape along the slits on the cover by using a 
paper cutter. Note that the cut shall not be too deep to avoid 
damaging the goods inside; 
3.  Open the carton and take out the foam pads; 
4.  Check the contents in the carton against the attached 
delivery list. 
 
 
Note
Do not damage the antistatic bags during the unpacking 
inspection process, as they may be useful in future storage of spare 
parts and return of failed parts.  
Properly dispose of the desiccants to keep them away from children.  
 
Goods Acceptance and Handover 
1.  Acceptance check 
Check the goods carefully one by one for acceptance 
according to the names, models, and quantities shown on 
the packaging list:  
There  must not be dents, bulges, scratches, peels, blithers, 
blisters or stains on the outer surface of the chassis.  
The surface paint on the cabinet  must not peel off or be 
scratched.  
The fastening bolts must be tight, not fall off or be displaced; 
The accessories and fittings needed for installation shall be 
complete. 
Arrange the inspected goods in good order by category.  
2.  Handover 
After inspection, the user representative and the engineering 
supervisor must sign on the Unpacking Inspection Report. In 
accordance with the contract, if the goods are to be kept by 
the equipment operator after inspection, the goods should be 
handed over to the equipment operator  after both parties 
sign on the Unpacking Inspection Report.