Carton Unpacking Procedure
1. Cut the straps by using the diagonal pliers;
2. Cut the adhesive tape along the slits on the cover by using a
paper cutter. Note that the cut shall not be too deep to avoid
damaging the goods inside;
damaging the goods inside;
3. Open the carton and take out the foam pads;
4. Check the contents in the carton against the attached
4. Check the contents in the carton against the attached
delivery list.
Note
:
Do not damage the antistatic bags during the unpacking
inspection process, as they may be useful in future storage of spare
parts and return of failed parts.
Properly dispose of the desiccants to keep them away from children.
Goods Acceptance and Handover
1. Acceptance check
Check the goods carefully one by one for acceptance
according to the names, models, and quantities shown on
the packaging list:
according to the names, models, and quantities shown on
the packaging list:
n
There must not be dents, bulges, scratches, peels, blithers,
blisters or stains on the outer surface of the chassis.
blisters or stains on the outer surface of the chassis.
n
The surface paint on the cabinet must not peel off or be
scratched.
scratched.
n
The fastening bolts must be tight, not fall off or be displaced;
n
The accessories and fittings needed for installation shall be
complete.
complete.
n
Arrange the inspected goods in good order by category.
2. Handover
After inspection, the user representative and the engineering
supervisor must sign on the Unpacking Inspection Report. In
accordance with the contract, if the goods are to be kept by
the equipment operator after inspection, the goods should be
handed over to the equipment operator after both parties
sign on the Unpacking Inspection Report.
supervisor must sign on the Unpacking Inspection Report. In
accordance with the contract, if the goods are to be kept by
the equipment operator after inspection, the goods should be
handed over to the equipment operator after both parties
sign on the Unpacking Inspection Report.