5  Installation Test and Final Acceptance 
Once the nanoCell has been installed and provisioned, it is necessary to verify nanoCell 
operation.  The following steps and procedure allow the technician to activate and test the 
nanoCell. 
5.1 Power-up 
Apply power to the nanoCell by placing the main circuit breaker to the on position.  Wait at least 
5 minutes to allow the nanoCell time to complete its boot process. 
5.2 Start-up 
Start-up of the nanoCell is automatic.  Once power is applied the nanoCell will go through its 
boot process (approximately 5 minutes) and will wait for authorization to transmit.  
5.3 System 
Configuration 
Using LMT, verify all of the system parameters from the site configuration sheet. 
a. 
b. 
c. 
d. 
Power on the laptop and connect the Ethernet cable to the Ethernet port located inside 
the right access panel. (As viewed from the front of the nanoCell). 
Verify that power has been applied to the nanoCell. 
Once the laptop has booted and power applied to the nanoCell, double-click the LMT 
icon located on the desktop of the laptop. 
The LMT software will launch and will display the screen as shown in Figure 12. 
 
Figure 12.  LMT Opening Screen 
e. 
f. 
g. 
Highlight the desired nanoCell and right-click. 
Select “Connect” from the drop-down menu.   
Right-click on the selected nanoCell and select “Parameters” from the drop-down 
menu.  This will bring of the dialog box as shown in Figure 13. 
 