Nova-436 Outdoor LTE TDD Base Station Installation Guide 
17 
 
2.  Connect the optical fiber to OPT interface in the wiring cavity. 
3.  Lay optical fibers along the wire groove, and stretch out the wiring cavity from OPT 
hole. 
The redundant fiber should wind neatly. 
3.6.5  Connect Ethernet Cable 
1.  Connect the Ethernet cable to ETH interface in the wiring cavity. 
2.  Lay Ethernet cable along the wire groove, and stretch out the wiring cavity from ETH 
hole. 
3.6.6  Connect Power Connector 
Because  it  is  not  sure  that  the  distance  between  the  installation  site  and  the  power 
supply device, the two ends of power adapter are bare terminal end. The operators need 
to make power cable according to the actual conditions on installation site, and assemble 
power plug and power terminal on two ends of power adapter. 
Strip 12mm insulating layer with wire stripper, which is used for connection to connector. 
It is recommended that the power cord length is kept below 100m (330 feet). 
The connection steps of power cable is as follows.   
1.  Assemble power plug. 
The  power  plug  will  be  installed  on  the  end  of  input  direction.  Refer  to  the 
identification  on  power  plug,  connect  live  wire,  neutral  wire,  and  ground  wire  to 
corresponding terminals separately, and tighten screws. 
2.  Assemble power terminal. 
The  power  terminal  will  be  installed  on  the  end  of  output  direction.  Refer  to  the 
following figure to connect live wire and neutral wire. 
 
3.  Connect the power cable to PWR interface in the wiring cavity. 
4.  The power cable lays along the lint slot, and stretch out the wiring cavity from PWR 
hole. 
5.  The input of the power adaptor connects to the outlet.