Texas Instruments TPS51200 Sink Source DDR Termination Regulator TPS51200EVM TPS51200EVM 데이터 시트

제품 코드
TPS51200EVM
다운로드
페이지 20
5.2
DDR2 Operation
5.2.1
DDR2 Source Load Regulation
5.2.2
DDR2 Sink/Source Transient
Test Procedure
www.ti.com
9. Set Switch S1 to the OFF position.
10. Decrease DC Source 4 to 0 V.
11. Decrease DC Source 3 to 0 V.
12. Decrease DC Source 2 to 0 V.
13. Decrease DC Source 1 to 0 V.
1. Set Switch S1 to the OFF position.
2. Ensure DC Source 4 is OFF.
3. Increase V
IN
(DC Source 1) from 0 V to 3.3 V at J1. This is the bias supply required for TPS51200
operation. Using V1, verify that V
IN
measures between 3.25 V and 3.35 V.
4. Increase VDDQ (DC Source 2) from 0 V to 1.8 V at J2. This is the reference input. Using V2, verify
that the VDDQ voltage is between 1.75 V and 1.85 V.
5. Increase VLDOIN (DC Source 3) from 0V to 1.8V at J3. This is the LDO input. Using V3, verify that the
VLDOIN voltage is between 1.75V and 1.85V. Ensure that the input wires are short and heavy (gauge
14 and lower).
6. Set Switch S1 to the ON position.
7. Set Load 1 to between 0 A and 2 A. Set Load 2 to between 0 mA and 10 mA.
8. Verify that V3 is between 1.75 V and 1.85 V, Adjust VLDOIN if necessary.
9. Use V4 and V5 to measure VTT, and VTTREF voltage. V4 uses for VTT at TP7 (+) and TP6 (–). V5
uses for VTTREF at TP18 (+) and TP19 (–). VTT and VTTREF both should be around 0.9 V.
10. Decrease Load 1 to 0 A,
11. Decrease Load 2 to 0 mA.
12. Set Switch S1 to the OFF position.
13. Continue on the test procedure
1. Remove Load 1 from J5.
2. Ensure two jumpers provided in the EVM to short pin1and pin2 are connected at location J7 and J8.
3. Increase DC Source 4 from 0 V to 5 V at J6. This is the bias supply required for transient load
operation. Using V6, verify that the 5VINPUT is between 4.95 V and 5.05 V.
4. Set Switch S1 to the ON position.
5. TPS51200 is now operating at sink (1.2 A) and source (1.2 A) load transient.
6. Verify V3 between 1.75 V and 1.85 V, Adjust VLDOIN if necessary.
7. Using V4 and V5 to measure VTT, VTTREF voltage. V4 uses for VTT at TP7 (+) and TP6 (–). V5 uses
for VTTREF at TP18 (+) and TP19 (–). VTT and VTTREF each should measure approximately 0.9 V.
8. Use scope probe to monitor VTT load transient regulation. The scope probe should be put at TP7 (+)
and TP6 (–) by setting to AC with 20 MHz bandwidth limiting. Use a vertical resolution of 20 mV per
division and a horizontal resolution of 200
µ
s per division. Use horizontal cursor to measure transient
load regulation. The measurement should ignore high frequency switch transition “spike”. Refer to
and
9. Set Switch S1 to the OFF position.
10. Decrease DC Source 4 to 0 V.
11. Decrease DC Source 3 to 0 V.
12. Decrease DC Source 2 to 0 V.
13. Decrease DC Source 1 to 0 V.
Using theTPS51200 EVM Sink/Source DDR Termination Regulator
10
SLUU323 – JUNE 2008