APC AP7900 Manual Do Utilizador
®
USER’S GUIDE
Switched Rack PDU
42
Outlet Settings for Outlets and Outlet Groups
How to initiate a control action
Web interface.
To control the outlets on your Switched Rack PDU
1. Select
Outlets
, and then
Control
on the navigation menu.
2. Mark the check-boxes for each individual outlet or outlet group to
control, or select the
All
Outlets
check-box.
3. Select a
Control Action
from the list, and click
Next >>
. On the
confirmation page that explains the action, choose to execute or cancel it.
Control Console.
Select
Outlet Control/Configuration
from the
Device
Manager
menu to display a list of outlets. For each outlet, the list indicates
whether it is a member of an outlet group.
1. Choose either or the following:
– To control one outlet and the outlet group, if any, to which it belongs,
select the number of the outlet, and then select
Control Outlet
.
– To control all outlets, select
Master Control/Configuration
, and
then
Control of ALL Outlets
.
2. Select a control action.
3. On the confirmation screen that describes the action to be executed,
3. On the confirmation screen that describes the action to be executed,
type
Yes
at the prompt to perform the action.
If you apply an outlet control action to outlets or outlet groups, the
following delays are used for the action:
following delays are used for the action:
• For an individual outlet (not in an outlet group), the action uses
the delay periods and reboot duration configured for that outlet.
• For a global outlet group, the action uses the delay periods
and reboot duration configured for the global outlet.
• For a local outlet group, the action uses the delay periods
configured for the lowest-numbered outlet in the group.