11
condensation,  both  tubes  must  be  well  insulated 
with  a  proper  insulation  material.  The  thickness 
of  the  insulation  should  be  a  minimum  8  mm. 
CAUTION
After  a  tube  has  been 
insulated,  never  try  to 
bend it into a narrow curve, 
as  this  may  cause  the  tube 
to break or crack.
5-6.Taping the Tubes
(1)  At  this  time,  the  2  refrigerant  tubes  (and 
electrical wire if local codes permit) should be 
taped  together  with  armoring  tape.  The  drain 
hose may also be included and taped together as 
1 bundle with the tubing.
(2)Wrap  the  armoring  tape  from  the  bottom  of  the 
outdoor  unit  to  the  top  of  the  tubing  where  it 
enters the wall. As you wrap the tubing, overlap 
half of each previous tape turn. (Fig.37)
(3)Clamp  the  tubing  bundle  to  wall,  using  1  clamp 
approx. every 120 cm.
NOTE
Do  not  wind  the  armoring  tape  too  tightly  since 
this will decrease the heat insulation effect. Also 
be  sure  the  condensation  drain  hose  splits  away 
from the bundle and drips clear of the unit and the 
tubing.
5-7. Finishing the Installation
After  finishing  insulating  and  taping  over  the 
tubing,  use  sealing  putty  to  seal  off  the  hole  in 
the  wall  to  prevent  rain  and  draft  from  entering. 
(Fig.38)
6.AIR PURGING
Air  and  moisture  remaining  in  the  refrigerant 
system have undesirable effects as indicated below. 
Therefore, they must be purged completely.
·pressure in the system rises
·operating current rises
·cooling efficiency drops
· moisture  in  the  air  may  freeze  and  block 
capillary 
     tubing
· water  may  lead  to  corrosion  of  parts  in  the 
refrigerant 
    system
6-1.Air Purging with a Vacuum Pump (for Test Run)
(1)Check that each tube (both narrow and wide tubes 
between  the  indoor  and  outdoor  units  have  been 
properly  connected  and  all  wiring  for  the  test 
run  has  been  completed.  Note  that  both  narrow 
and wide tube service valves on the outdoor unit 
are kept closed at this stage.
(2)Using an adjustable wrench or box wrench, remove 
the  valve  caps  from  the  service  valve  on  both 
narrow and wide tubes.
(3)  Connect  a  vacuum  pump  and  a  manifold  valve 
(with  pressure  gauges)  to  the  service  port  on 
the wide tube service valve.(Fig.39)
(4)With  the  “ Lo” knob  of  the  manifold  valve  open, 
run  the  vacuum  pump.  The  operation  time  for  the 
vacuum  pump  varies  with  tubing  length  and  the 
capacity  of  the  pump.  The  following  table  shows 
the amount of time for evacuation:  
CAUTION
Be sur e t o use a m a n i f o ld 
valve  f o r  air  p u r g i n g .  I 
f it i s
Not av a i l a b l e , use a s t op 
valve  for  th i s  p u r p o s e. 
The  
“ Hi” k n o b  o f  t h e 
m a n i f o l d  v a l v e  m u s t 
Min.
8mm
Insulation
Thickness:
min.8mm
Fig.36
Fig.35
Fig.37
Insulated tubes
Clamp
Fig.38
Tubing
Apply putty here
Fig.34
Outdoor unit
Insulation
Indoor unit
Spanner
Torque wrench