Upgrading the Cisco ONS 15600 SDH to Release 9.0
78-18839-01
DLP-  U446 Accept the New Load
Grant always—Installs the public-key certificate and does not delete it after the session is over. 
Cisco recommends this option.
View Certificate—Allows you to view the public-key security certificate.
Step 3
Return to your originating procedure (NTP).
DLP-U446 Accept the New Load
Step 1
If CTC is not already running, start CTC.
Step 2
In node view, click the Maintenance tab and then click the Software button.
Step 3
Click the Accept button. The acceptance process will take approximately 2 to 5 minutes.
Note
You can reject the new software load by clicking the Cancel button. 
Note
If the Cancel button is not active, the standby TSC has not finished acquiring the active timing 
reference. The acquire process can take approximately 10 to 15 minutes. When the acquire 
process completes, the Cancel button becomes active.
Step 4
On the Maintenance tab, click the Software button and verify the version:
a.
Click the Info button.
b.
In the Current Software Info dialog box, verify that the TSC B Working field shows the correct 
version. The TSC B Protect field should show the previous version. 
c.
If the TSC B Working and TSC B Protect fields show none, click OK and click the Info button again 
after several minutes. Repeat until the TSC B software versions appear.
d.
Click OK.
Step 5
Back up Software 8.0 using the 
, substituting Software R9.0 for Software R8.0.
Step 6
Return to your originating procedure (NTP).
Purpose
This task upgrades the standby TSC card.
Tools/Equipment
PC or UNIX workstation
Prerequisite Procedures
Required/As Needed
Required
Onsite/Remote
Onsite or remote (but in the presence of the workstation)
Security Level