5  POST-INSTALLATION INSPECTION 
Verify the following before proceeding with power-up of the system: 
a.  The cabinet or rack has been installed and grounded per the Site Grounding and Lightning Protection 
Guidelines Manual, AE/LZT 123 4618/1. 
b.  All safety ground connections are: 
i.  Properly crimped. 
ii.  Connected to the proper connection points on the equipment. 
iii.  Connected to the ground bus bar using gradual bends in an upward fashion. 
iv.  Nut and/or bolts securing the ground lugs are sufficiently tightened. 
c.  All AC power cables have been labeled and installed per Section 4.5. 
d.  All rear panel control cable connections have been labeled and installed per Section 4.5 
e.  All modules have been installed per Section 4.6. 
f.  All front panel power switches on the PSU units have been set to the Off position. 
g.  All front panel RF antenna connections are labeled and installed per Section 4.7. 
h.  Verify  all  receive  and  transmit  antenna  ports  are  connected  to  50  ohm  load  resistors  of  sufficient 
power rating. 
 
CAUTION
 
To  prevent  unintentional  or  malicious  interference  to  other  radio  systems,  the  receive 
and transmit antenna ports of all new installations should first be connected to 50 ohm 
load  resistors  of  sufficient  power  rating  until  the  system  is  programmed  to  the  proper 
operating frequencies and ready to be deployed.