SOLAR CONTROLLER AND SOLAR MONITOR 
2007 October 
SK6203 Rev B 
COMMISSIONING 
When the electrical supply is switched on to the solar control unit at start up: 
• 
If there is no solar gain, the circulator will not activate and the green LED 
will emit a slow pulse. 
The slow pulse indicates the circulator is not activated and the power to the 
solar control unit has been on for less than 48 hours. 
• 
If there is solar gain, the circulator activates and the green LED will emit a 
series of three (3) flashes. 
The three (3) flashes indicate the circulator is operating and power to the 
solar control unit has been on for less than 48 hours. 
• 
The circulator will operate at full speed for approximately fifteen (15) 
seconds. If the red LED is emitting a rapid pulse, the circulator may operate 
at full speed for up to ten (10) minutes. 
After fifteen (15) seconds or after the red LED has extinguished, the solar 
controller will commence to pulse the circulator to control the flow rate 
through the collector circuit and achieve a constant temperature rise across 
the collector(s). It is normal operation for the circulator to experience a 
pulsing effect. 
• 
The red LED may emit a rapid pulse for a short period. 
This indicates a temperature difference between the hot sensor and cold 
sensor of greater than 40°C and does not represent a fault code. This is the 
result of a build-up of heat and increase in water temperature in the 
collector prior to the switching on of the electrical supply to the solar control 
unit. 
 
The rapid pulsing of the red LED will cease as the water circulates and the 
heat is dissipated. This should be within four (4) to five (5) minutes of start 
up, but may take up to ten (10) minutes. 
 
If the red LED does continue to emit a rapid pulse for longer than ten (10) 
minutes, this may indicate water is not circulating through the collectors and 
solar circuit: 
„
 
switch off the electrical supply at the power outlet to the solar control unit 
„
 
repeat the procedure to bleed the solar collectors 
„
 
switch on the electrical supply at the power outlet to the solar control unit