♦  Put the mains input miniature circuit breaker (no.
 
2, 
p. 27/28) in the “OFF” position. 
Connect the UPS terminal “     /
 
PE
 
“ (earth) with the 
corresponding earth terminal in the distribution cabinet. 
Connect the supply cable from the MI distribution to the 
terminals 1.1 of the UPS that are marked with “INPUT”: 
 
/ PE   
 =   Ground 
 
N  
 
 =   Neutral conductor 
 
L1/L2/L3   =   Phases 
 
Check the jumper between “JP1” and “JP2” 
(terminal designation “JUMPER”). 
Only remove the cable if you want to use the UPS 
in parallel operation with further PROTECT 1. units 
of the same type (see also chapter 9). 
5.3.3 
Preparation of the Output Cabling 
Before you connect the loads to the UPS, the nominal output 
listed on the nameplate must be greater than or equal to the 
sum of the load power outputs. 
The output of the PROTECT 1. should supply further separate 
circuits in a subdistribution. Make sure that the fuse protection is 
selectively designed (see also chapter 5.2.2). 
For the connection between the PROTECT 1. and the 
subdistribution, cable cross-sections acc. to the table 
“Connection Cross-Sections and Fuse Protection” on p. 31 
must be used. In the subdistribution, note at least the following 
information: 
♦  Maximum permissible total load 
♦  Maximum permissible load of the individual load circuits 
i
 
In the case of a common distribution cabinet 
(circuits with mains as well as UPS voltage), label 
each circuit with the respective supply (mains or 
UPS).