Справочник Пользователя для AEG 10000

Скачать
Страница из 58
31 
5.3.2 
Connection of the one phase mains connector 
To protect the personnel during installation, ensure that the 
connection takes place und the following precautions: 
♦  No mains power present. 
♦  Loads are switched of. 
♦  The PROTECT C. is switched of (display completely 
off). 
To activate the PROTECT C. execute the following steps: 
♦  Set Manual bypass „Maintenance Switch“ to “Bypass” 
on the rear of the UPS. Remove the four screws of the 
cover (Pos. 2, page 26). 
♦  Set the mains input circuit breaker (Pos. 3, page 26) to 
position “OFF”. 
Connect the UPS terminal  „    /
 
PE
 
“ (Ground) with the 
associated ground terminal in the distribution cabinet.  
Connect the mains supply cable with the NS distributor to the 
„INPUT“ terminal in the UPS: 
 
 
/ PE   =   Ground 
 
N  
 =   Neutral line 
 
 =   Phase 
 
Check the bridge between „JP1“ and „JP2“ 
(Terminal label „JUMPER“). 
Only remove the cable, when using the PROTECT 
C. in parallel operation with appliances of the 
same type (see chapter 9). 
5.3.3 
Preparation for the load connection 
Before connecting the loads to the UPS, it is necessary to 
ensure that the rated power of the label of the UPS is higher 
or equal to the sum of the power consumption of the loads. 
The output of the PROTECT C. should supply the sub 
distribution in separate power circuits. Check for a selective 
protection of the circuits.  
For the connection between PROTECT C. and the sub 
distribution cable diameters according to table 1 on page 30