Справочник Пользователя для Checkpoint Systems Inc. EVOLVEF10

Скачать
Страница из 71
F10 Installation Manual 
                         Rev. *60          
 
15 of 71
 
Electronics Enclosure Placement Requirements 
•  Locate the electronics enclosure no further than 12.2m (40 linear-feet) or 15.2m 
(50 cable-feet) from the antenna(s) to allow for bends in the conduit run.  
•  If wall-mounting is ideal, mount the electronics enclosure approximately 1.8m [6ft] 
above the floor to reduce RF-interaction with wiring in either the ceiling or the floor.  
Electronics mounted to the ceiling can potentially have a high RF-interaction with the surrounding 
environment (e.g., metal rafters or power cables), and therefore, may not perform optimally here. 
Observe locations of active noise sources including deactivators. 
Environmental Considerations 
F10 systems are only approved for indoor installations only. For a first floor (ground level) 
installation where the slab will be on grade (i.e., directly above the natural ground), we 
recommend the concrete be poured above a vapor barrier to prevent moisture from rising. 
The store's architect will recommend the maximum permissible loading in the floor area where 
F10 antennas are physically installed. The architect must consider such factors as anticipated 
traffic over the floor and the material characteristics of the flooring (if covered by concrete).  
The guidelines included in this guide assume installation into concrete (typical), but the antennas 
may be placed directly on concrete if flooring, such as finished hardwood, laminate, tile or stone, 
conceals the system below. If a wooden floor is placed on top of the system, the weight of the 
floor should not rest on the antenna(s). Moreover, with all installations, the concrete and other 
materials above the antenna(s) cannot be metallic. For example, wire mesh cannot be used for 
reinforcement above the concrete. Metallic walk-off mats should not be placed above the system.  
  Note: Tile grout and mortar used to fill antenna trenches MUST BE non-metallic and non-magnetic grout.  
Another environmental consideration is a metal security gate. For installations where the drop 
down or sliding gate could cause a phantom alarming issue, a Badge Board II (CKP P/N 7528451) 
and a Gate Inhibit Switch (CKP P/N 7140188) should be installed. Discuss with Product 
Management and customers.   
As for the electronics, typical indoor conditions must be met. Operating temperature is 0°C to 
+40°C [32° to 104°F]. Permissible humidity range is 10 to 75%.  
Site Survey Conclusion 
Overall, the site survey is an opportunity to gather details and share information required for the 
proper installation workflow. Before leaving the test site, the location of the electronics enclosure, 
floor cuts (trenches or “channels”), and/or conduit runs (see note) should be documented. 
Using the information in the following chapter, draw up a plan with exact dimensions. In addition 
to floor cuts, the power outlet locations (or hardwire into electrical for plenum installation) should 
be planned. Coordinating with site contractors facilitates easier installation. 
   Note:
 
 
For the F10 System, it is required that the coax cable is ran through ENT Tubing (conduit). 
Communicate with the contractor (and/or store personnel) before concrete has been poured. This 
crucial action will allow the coax cable to be easily routed through the conduit. 
  Caution: Ensure wire run does not exceed the maximum distance to the electronics’ planned location.