 Chapter 
Commissioning 
 
Commissioning 
 
4.1 
Introduction 
 
This section describes the power-on, configuration and RF test procedures for the DRU-200. 
 
 
4.2 
Test Equipment 
 
Please refer to Table 4-1 for a list of required test equipment.  Operating instructions for 
test equipment are not included in this manual.  Only precautionary notes or special test 
equipment settings required for measurement accuracy are included. 
 
Table 4-1 Test Equipment 
Type 
PC/Laptop 
 
 
4.3 
Installation Verification 
 
Please check the following before turning on the DRU-200: 
 
•  Verify that no equipment was damaged during the installation. 
•  Verify that there are no sign of water or debris in the cabinet. 
•  Verify that the ground conductor has been connected to the repeater cabinet ground 
stud. 
•  Verify that the main AC power cable has been connected to the repeater cabinet PDU 
correctly. 
•  Verify that the electronics compartment components (assemblies), which were 
packaged separately, have been installed correctly. 
o
 
Verify that the components are in the correct locations. 
o
 
Verify that the ground, communications, RF and power wires/cables have been 
connected correctly. 
•  Verify that all HPA compartment components (assemblies), which were packaged 
separately, have been installed correctly. 
•  Verify that all external input signals have been connected to the correct interfaces. 
•  Verify that the PTSN phone line cord has been connected to the surge protector 
correctly (where applicable). 
•  Verify that any external alarm contacts/sensors have been connected to the external 
alarm terminal block correctly (where applicable). 
•  Verify that the broadcast antenna(s) and transmission line(s) have been swept and 
connected to the correct RF output port. 
 
 
 
SX03-10000-01-M01 4-1