4-2-1-2  Mezzanine Mount 
 
In a mezzanine mount application, review the following items 
before installation begins. First, verify the SGB mounting 
locations match the mezzanine supports. Verify that the 
mezzanine is capable of supporting the blender with a full load 
of material and vacuum loading equipment installed. 
 
Important!  
While in operation, the SGB applies horizontal and vertical 
pressures to the mounting flange. If there is a question as 
to the mechanical stability of a mounting flange, contact 
Sterling’s Mechanical Engineering department. 
 
Ensure that the gravity feed tube is installed in a vertical 
position, so that the materials will gravity flow to the extruder 
hopper. Use aluminum tubing or smooth wall flex hose. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
If possible, use rigid tubing.  Some flex hose will tend to sag and 
generate static that could cause de-mixing between the blender 
and the extruder. 
 
Make sure that adequate space is around the blender (36” 
recommended) to allow proper cleaning, servicing, etc. 
MEZZANINE (SUPPLIED BY
CUSTOMER)
OFC WITH RE-LOAD VALVE
(PURCHASED SEPARATELY)
GRAVIMETRIC BATCH BLENDER