SGB Batch Blender with Mitsubishi Controller 
 
4-2-1-3  Floor Mount (Central Blender) 
 
In a floor mounting application, ensure adequate clearance for 
all blender operations and maintenance. The operator and 
maintenance personnel must have access to parts of the 
blender. If necessary, it is the customer’s responsibility to 
provide adequate, safe work platforms around the blender to 
meet state and local safety codes. Using proper lifting 
equipment, lift the SGB in place. 
 
Important!
  
The blender must be securely fastened to the floor before 
operating. 
 
Sterling assumes no responsibility for any damages 
resulting from improper installation or improper handling 
during installation

 
 
Make sure that the blender is securely mounted to the floor 
before installing loading equipment, loading with material and 
starting. 
 
Make sure that the blender location is adequately away from 
high traffic aisles, and that fork trucks, etc. cannot damage the 
blender. Ensure that normal day-to-day operations will not place 
the blending system at risk of damage. 
 
 
TYPICAL CENTRAL BLENDER LAYOUT 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Supply Hoppers
Floor Stand
Take-off Compartment
Surge Bin
Blender
Pneumatic Slide Gate Below Mixer