5.2 Boiler Sizing
• Verify you have selected boiler with  proper capacity 
before continuing installation. AHRI Rating of selected 
boiler should be greater than or equal to calculated 
peak heating load (heat loss) for the building or area(s) 
served by boiler and associated hot water heating 
systems. See Sea Level Ratings - Natural and Propane 
Gases”  Section 4.
• Heat loss calculations should be based on approved 
industry methods.
5.3 Considerations for Boiler Location
Before selecting boiler location consider following.
• Supplied with correct type of gas (natural gas or 
propane).
• Connected to suitable combustion air intake piping 
system to supply correct amounts of fresh (outdoor) air 
for combustion (15’ minimum equivalent length/100’ 
maximum equivalent length).
• Connected to suitable venting system. (15’ minimum 
equivalent length/100’ maximum equivalent length).
• Connected to suitable hot water heating system.
• Supplied with suitable electrical supply for all boiler 
motors and controls.
• Connected to properly located thermostat or operating 
control (not included with boiler).
 WARNING
Fire hazard. Do not install on carpeting. Failure to 
follow these instructions could result in death or 
serious injury.
!
  
• Placed on level surface (must NOT be installed on 
carpeting).
• Pitch condensate drain line down to floor drain or 
external condensate pump with reservoir at ¼” per foot 
(wood frame or blocks may be used to raise boiler).
5.1 Before Boiler Installation
1. 
Boiler is equipped for residential installations. If 
used for commercial applications, additional code 
requirements must be adhered to for installation. This 
may require additional controls including but not limited 
to a low water cut off, a manual reset high temperature 
limit, and wiring and/or piping modifications. 
2. 
Never vent products of combustion from this boiler to 
enclosed space. Always vent to outdoors. Never vent to 
another room or to inside building.
3. 
Keep boiler area clean of debris and free of combustible 
and flammable materials.
4. 
Proper through wall or through roof combustion venting 
shall be in accordance with materials and methods 
described in this manual. Installation must comply with 
local codes.