Utica Boilers UB95M-200 Installationsanweisungen

Seite von 52
7.2 Supply & Return Lines
See Appendix A for piping examples.
• Packaged boiler set to receive 1¼” NPT  return piping 
from rear of unit with option for left or right return 
connections. 
• Use two furnished dielectric unions at boiler supply and 
return connections between copper system piping and 
boiler. Do not install copper supply and return piping 
directly into aluminum boiler casting due to galvanic 
corrosion between dissimilar metals.
• 1¼” NPT supply piping exits boiler jacket at top of unit.
• Some boilers supplied with circulator pump and 
isolation valves are furnished in a carton inside boiler 
cabinet and can be installed at installer preferred 
location.
7.1 Clean System First
Before connecting boiler to heating system, clean and flush 
system thoroughly. Verify system is free of sediment, flux 
and any residual boiler water additives.
Systems having antifreeze not recommended must be 
completely flushed to insure no old antifreeze remains. In 
older systems obviously discolored, murky or dirty water; 
or pH reading outside acceptable range (between 7.0 and 
8.0) are indications system should be cleaned or treated. 
Thoroughly flush system with clean water to remove any 
sediment or contaminants. Sludge and iron oxide deposits 
can cause rapid breakdown of inhibitors.
Flushing with clean water. If chemical cleaners are used, 
use only those recommended for use with aluminum 
boilers. Follow chemical cleaner manufacturer’s instructions 
completely.
DO NOT
 mix different manufacturer’s products.
• When boiler installation is for new heating system, 
install all of radiation units (panels, radiators, 
baseboard, or tubing) and supply and return mains. 
• After all heating system piping and components have 
been installed, make final connection of system piping 
to boiler. 
• Hot water boiler installed above radiation level, or as 
required by the Authority having jurisdiction, must be 
equipped with low water cut off device. This boiler is 
factory equipped with manual reset probe type low 
water cutoff.
• Periodic inspection is necessary per low water cut off 
manufacturers specific instructions.
7 - NEAR BOILER PIPING
9