RECEIVING, INSPECTION AND HANDLING 
 
 
 
RECEIVING AND UNPACKING
 
 
The circuit breaker units are subjected to factory 
production testing prior to being packed and 
shipped. 
 
ACCEPTANCE INSPECTION 
 
Confirm that the circuit breaker and cell units are 
complete, correct as specified and undamaged 
from shipment and handling. 
 
Upon receipt of the equipment, do the following: 
 
1)  Make an immediate inspection for damage 
that might have occurred during shipment. If 
damage is discovered, it should be noted 
with the carrier prior to accepting the 
shipment, if possible. 
 
2)  Carefully unpack the equipment sufficiently to 
check for missing parts or concealed 
damage. 
  
3)  Check for the presence of accessories that 
are shipped with the circuit breaker and cell: 
 
-  Charging Handle (Fig. 5) 
-  B9 Grease (Fig. 6) 
-  Control Wire Harness (Fig. 7) 
 
3)  Keep the circuit breaker and cell upright. 
 
Never lay the circuit 
breaker or cell on its side 
or upside down.  This may 
cause damage.  
 
4)   File a claim with the carrier for any damaged 
or missing items and immediately notify the 
nearest Toshiba representative. 
 
Do not install or energize 
equipment that has been 
damaged.  Damaged 
equipment can fail during 
operation, resulting in fire 
and explosion.
 
 
 
 
 
 
Fig. 5  Charging Handle 
 
Fig. 6  B9 Grease 
 
Fig. 7  Control Wire Harness 
 
 
    CAUTION 
    WARNING 
CTi Automation - Phone: 800.894.0412 - Fax: 208.368.0415 - Web: www.ctiautomation.net - Email: info@ctiautomation.net