Avaya 03-300430 User Manual

Page of 2574
Communication Manager Maintenance-Object Repair Procedures
1966 Maintenance Procedures for Avaya Communication Manager 3.0, Media Gateways and Servers
 
FAIL 
(
cont’d
)
Procedure 2: - This procedure attempts to isolate the Serial Bus failure to a 
particular set of carriers. Only the circuit packs in selected carriers are 
checked. Procedure 2 is organized into two parts. Part 1 attempts to clear 
the Serial Bus fault by replacing all the bus cabling and terminators within a 
port-network. Part 2 attempts to isolate the fault to a particular carrier by 
extending the Serial Bus from the A carrier to additional carriers one at a 
time.
!
WARNING:
WARNING:
Power must be removed from the entire port network before 
any cables or terminators are removed. Failure to follow this 
procedure can cause damage to circuit packs and power 
supplies, and can be hazardous to the technician.
Part 1:
1. If spare TDM/LAN Cable assemblies and TDM/LAN Bus Terminators 
are not available, go to Part 2 of this procedure.
2. Power down the port network.
3. Replace all of the TDM/LAN Cable Assemblies and both TDM/LAN 
Bus Terminators.
4. Restore power to the port network.
5. Run list configuration power-supply C to determine if the 
Serial Bus fault is still present.
6. If the Serial Bus fault is resolved, the procedure is completed. 
Otherwise, go to Part 2.
Part 2:
1. Terminate the TDM/LAN Bus so that it extends only across the carrier 
that contains the A carrier TN2312BP IPSI.
2. Determine if the Serial Bus fault is still present by running list 
configuration power-supply C.
Table 720: Test 1531 Serial bus status  (continued)
Error
code
Test
result
Description and recommendation
 4 of 5