Billing Cycle
This approach is recommended when all meters in a billing cycle are required to reset 
demand.
Billing Cycle membership changes will NOT automatically be reflected in the next demand 
resets. 
Virtual Addressing Group
This approach is recommended when not all meters in a billing cycle require a demand reset.
Virtual Addressing Group membership changes will automatically be reflected in next 
demand resets.
This approach requires additional management (creating of virtual addressing groups, 
manually adding meters to virtual addressing groups).
Sending the Demand Reset Commands
The System Setting Scheduled Demand Reset Window to send Commands (Figure 6 - 1) deter-
mines when the Demand Reset Schedule will be sent to endpoints. This value must be between 2-21 
days and has a default value of 21 days. The value used for this setting is business decision made by 
the utility to help ensure that meters are included in upcoming demand resets. 
Figure 6 - 1. Scheduled Demand Reset Window to Send Commands
Whether or not newly added meters receive this schedule may depend on what type of group was 
used for membership:
Billing Cycle Membership
Meters added to the billing cycle after the commands have been sent to the meter will NOT 
be included in the upcoming demand reset.
Meters removed from the billing cycle after the commands have been sent to the meters will 
still be included in the upcoming demand reset.
For example, if the Scheduled Demand Reset Window to send Commands is 5 days and:
The Demand Reset date for Billing Cycle 1 is scheduled for 11/10.
Scheduled Commands are sent on 11/5 to all meters in Billing Cycle 1.
A meter added to Billing Cycle 1 on 11/8 will not receive the schedule for 11/10.
Virtual Addressing Group
Meters added to the Virtual Addressing Group after the commands have been sent to the 
meter will be included in the upcoming demand reset.
Meters removed from the Virtual Addressing Group after the commands have been sent to 
the meters will not be included in the upcoming demand reset.
For example, if the Scheduled Demand Reset Window to send Commands is 5 days and:
The Demand Reset date for the Virtual Addressing Group is scheduled for 11/10.