Landis+Gyr Technology Inc. ER6R1S4 User Manual
Draft
Chapter 6 - Scheduled Demand Reset
Landis+Gyr
68
98-1723 Rev AB
User Guide
•
Repeat on day [] of each month. The Scheduled Read can be set to repeat on the same
date of each month. Enter a number from 1 to 31.
date of each month. Enter a number from 1 to 31.
•
Repeat [] day(s) before the end of each month. The Scheduled Read can be set to
repeat every month on a specified number of days before the last day of the month.
repeat every month on a specified number of days before the last day of the month.
If repeating...
•
Repeat until []. The Scheduled Read can be set to repeat until the user specified date by
clicking the calendar icon and selecting the end date for the Scheduled Read.
clicking the calendar icon and selecting the end date for the Scheduled Read.
7. Click Save, to save the new Scheduled Read. The Scheduled RFU FocusAX Reads scheduled
will open, displaying the new scheduled read.
Changing/Deleting Schedules
A future schedule can be changed, deleted or copied on the main Scheduled Reads page.
Schedule Changes.
•
If the temporary commands have already been sent down to the meter, Command Center
will issue commands to remove the original schedule from the endpoint.
will issue commands to remove the original schedule from the endpoint.
•
If the new schedule dates are within the next Scheduled Demand Reset Window to send
Commands (default 21 days), Command Center will send the schedule to the endpoint.
Commands (default 21 days), Command Center will send the schedule to the endpoint.
Schedule Deletes.
•
If the temporary commands have already been sent, Command Center will issue commands
to remove the original schedule from the meter.
to remove the original schedule from the meter.
Scheduled Command Workflow Process
Once the Demand Reset is scheduled, X days before the Demand Reset date (X = Window to Send
Scheduled Commands) Command Center will issue a Send Scheduled Command command. The
Process Setting RF Scheduled Demand Reset Workflow dictates how frequently Command Center
will re-issue the Demand Reset commands to endpoints that have not acknowledged receipt of the
schedule. By default, this process runs every 30 minutes with a maximum number of retries equal to
5.
Scheduled Commands) Command Center will issue a Send Scheduled Command command. The
Process Setting RF Scheduled Demand Reset Workflow dictates how frequently Command Center
will re-issue the Demand Reset commands to endpoints that have not acknowledged receipt of the
schedule. By default, this process runs every 30 minutes with a maximum number of retries equal to
5.
Monitoring Demand Resets
Command Center monitors two aspects of the demand reset process:
•
Did the schedule reach the meters?
•
Did the demand reset occur as scheduled?
Verifying Receipt of the Schedule
Individual verification that the Send Scheduled Command was issued and reached a designated
meter is visible on the individual Gridstream RF Endpoint Information - Manage tab. Group
verification of the receipt of the scheduled commands by designated meters can be done via the
Endpoint Report for Scheduled Reads with Demand Reset.
meter is visible on the individual Gridstream RF Endpoint Information - Manage tab. Group
verification of the receipt of the scheduled commands by designated meters can be done via the
Endpoint Report for Scheduled Reads with Demand Reset.