2. 
3.   
. 
4.  Verify the following: 
-  The power supplies are operational, indicated by the illumination of the 
green light below the power cord connector. 
The server’s fan and blower are operating. 
-  The adapter cards (if installed) are properly installed in their slots, and 
each initializes (is enabled by the appliance software) without problems. 
-  There is network connectivity to the server. 
When each of these conditions is met, proceed to 
. If any of these conditions are not met, refer to 
Troubleshooting
5.  Power down the server and remove all cables prior to installing it in the rack. 
Mounting the SV Director Server in a 4-Post Rack 
To install the SV Director Server in a 4-post rack, follow these steps: 
Warning! When the unit is installed in a rack and is fully extended on its slide 
rail, it is possible for the rack to become unstable and tip over, which could cause 
serious injury. To eliminate the risk of rack instability from extending the rail or in 
the event of an earthquake, you should affix the rack to the floor. 
Figure 26 shows the rails and brackets that you need to install the SV Director 
Server in a 4-post rack. Figure 27  lists the contents of the 4-Post Rack Mount 
Hardware Kit that comes with the SV Director Server. 
Figure 26.  4-post Rails and Brackets 
 
No. 
Description 
Rear-mounting bracket of outer slide rail  
Front-mounting bracket of outer slide rail  
Inner slide rail