3.  Switch ON the output switch Q1 (Pos. I) on each unit
 When 
the 
last 
Q1 will be closed, the output will be supplied by
the mains through all bypass
 
LP 33         40kVA  P1 
APPLICAT. ON UTILITY 
= 70% 
 
 
Verify, selecting the screen METERING/Udcp and Udcn, that the 
booster voltage has reached about 215 VDC. 
 
Udcp=215V Udcn=215V 
Ubp=164V Ubn=164V 
 
 
Charge level 
=  100% 
Autonomy = 
800min 
 
4.  Switch ON the inverter on the first unit entering the screen
 
MENU/COMMAND MENU/INVERTER ON 
 
COMMAND MENU 
INVERTER ON * 
INVERTER OFF 
 
 
5.  Switch ON the inverter on the other units in the same manner
(Do not start the next inverter until the sequence of the previous
one ends – about 10 seconds).
 
 
COMMAND MENU 
INVERTER ON * 
INVERTER OFF 
 
 
Some seconds later the load will be transferred on inverter and
the main screen of each unit will display: 
APPLICATION ON UPS 
 
LP 33          40kVA  P1 
APPLICATION ON UPS 
= 70% 
 
 
END OF PROCEDURE 
 
 
 
 
 
 
 
NOTE ! 
Even if the UPS is delivered with the battery fully charged, they could be partially 
discharged during transportation or storage. 
It is recommended to recharge the battery during a few hours in order to provide the 
complete battery
 energy stored to the load in the event of mains failure.