GE LP 33 Manual De Usuario

Descargar
Página de 57
Modifications reserved 
Page 43/57 
OPM_LPS_3UO_30K_40K_0US_V010.doc 
Operating Manual LP 33 Series 30 & 40 kVA 
 
7.2  PROCEDURES FOR PARALLEL SYSTEM LP 33 Series 
 
 
7.2.1 
Parallel System start-up of the LP 33 Series 
 
 
Before connecting hazardous voltages, make sure that: 
•  The connection to the electrical system has been performed by qualified personnel; 
•  The equipment frame has been correctly grounded to the main earth
•  Make sure that mains input protection is removed; 
•  All the panels removed to allow the UPS connection have been correctly reinstalled; 
•  The UPS switches Q1 and Q2 are OFF (Pos. 0); 
•  The battery fuses F5, F6, F7 (and eventual external fuses in case of external battery) 
are removed. 
 
This procedure must be performed for the first start-up following the installation, with all the units 
completely switched Off and not powered. 
 
This procedure presupposes that the load is not yet supplied by the UPS system. 
 
 
NOTE ! 
The UPS can be started-up using the battery supply in case the input mains should be 
unavailable. 
To avoid an incidental battery
 discharge, it is recommended to proceed to the UPS 
start-up having the input mains
 available. 
 
 
 
1.  Switch ON the mains power for each unit at the input 
distribution panel. 
As a result each unit performs a self-test and the LCD will show 
the following screen: 
 
EXECUTING MAINBOARD 
SELF TEST 
00000000000 
SELF TEST OK! 
 
 
 
The LCD screen will display the number of the unit in the parallel
system (P1P2P3 or P4)
   
 
   
 
 
NOTE ! 
In case the alarm “4410 - Mains bypass out of 
tolerance”
 persists, please contact your Service 
Center
 
 
 
2. Insert 
the battery fuses F5, F6, F7 (and eventual external fuses in case of external battery) on 
each unit. 
 
Continue