Operating Manual LP 33 Series 30 & 40 kVA 
7.2.3 
Start-up following the operation on maintenance bypass (Q2) 
 
This procedure presupposes that the load is powered by the manual bypass switch: 
•  The inverter is switched OFF; 
•  The manual bypass switch Q2 is switched ON (Pos. I); 
•  The output switch Q1 is switched OFF (Pos. 0); 
•  The battery fuses F5, F6, F7 (and eventual external fuses in case of external battery) are removed. 
 
 
 
1.  Insert the rectifier input fuses F1, F2, F3 and the battery fuses F9, F10, F11 / F13, F14, F15 (and 
eventual external battery fuses) on each unit. 
 
2.  Switch ON the output switch Q1 (Pos. I) on each unit
 
3.  Only in case it has been previously activated (* present beside 
the text RESET TOTAL OFF), restore the command total off 
on 
any one of the units
 by entering the screen: 
MENU/RESET TOTAL OFF 
 
LED TEST 
RESET TOTAL OFF 
* 
 
 
 
Udcp=215V Udcn=215V 
Ubp=164V Ubn=164V 
 
 
Charge level 
=  100% 
Autonomy = 
800min 
4.  Open the maintenance bypass switch Q2 (Pos. 0) on each 
unit. 
 Verify, selecting the screen METERING/Udcp and Udcn, that the 
booster voltage has reached about 215 VDC on each unit. 
 
 
 
5.  Switch ON the inverter on each unit entering the screen
MENU/ COMMAND MENU /INVERTER ON 
(Do not start the next inverter until the sequence of the 
previous one ends – about 10 seconds). 
 
COMMAND MENU 
INVERTER ON * 
INVERTER OFF 
 
 
LP 33          40kVA  P1 
APPLICATION ON UPS 
= 70% 
 
The  load will be automatically transferred from mains to the 
inverters as the needed power requested from the applied load 
is achieved on inverter side. 
The main screen of each unit will display: 
APPLICATION ON UPS
 
 
 
 
END OF PROCEDURE