18 
 
 
If the outlet is indoors, place the power adaptor indoors. 
 
If the outlet is outdoors, place the power adaptor in a water proof box. 
4.  After the cable connection is complete in the wiring cavity, fasten the screws on the 
cover to close the wiring cavity using M4 cross screwdriver. 
4.6.7  Connect Ground Cable 
Make the grounding cable according the actual situation of the installation site. 
The  mBS1105  provides  two  grounding  screws,  which  is  located  on  the  bottom  of  the 
base station, as shown in Figure 4-3. 
Figure 4-3 Location of Grounding Screws 
 
 
1.  Unscrew  one  grounding  screw,  connect  one  end  of  the  grounding  cable  to  the 
grounding screw, and fasten it again. 
2.  The other end of the ground cable needs to connect to a good grounding point. 
 
Install Antenna Feeder System 
4.7
There  are  two  kinds  of  outdoor  antennas,  omnidirectional  outdoor  antennas  and 
directional  outdoor  antennas,  whose  installation  will  be  introduced  in  the  following, 
respectively. 
4.7.1  Install Omnidirectional Antennas 
One  should  pay  attention  to  the  followings  while  installing  the  omnidirectional  outdoor 
antenna: 
 
The  diameter  of  the  pole  for  omnidirectional  outdoor  antennas  is  required  to  be 
35mm ~ 50mm. A typical case is to use the 50mm-diameter round-steel-made pole 
(with details depending on the specific antenna type). 
 
Make sure that the top of pole and the clamp beneath the antenna are at the same 
level, after installing the omnidirectional outdoor antenna on the pole.