19. 
Do one of the following: 
Close or install the tower bezel, as needed. 
Slide the server back into the rack. 
20. 
Connect all power cords to the server. 
21. 
Connect power cords to the power source. 
22. 
Power up the server (on page 
 
Storage controller option 
  
 
IMPORTANT:
  For additional installation and configuration information, refer to the 
documentation that ships with the option. 
  
To install the component: 
1. 
Power down the server (on page 
). 
2. 
Do one of the following: 
Open or remove the tower bezel, as needed ("
). 
Extend the server from the rack (on page 
). 
3. 
Remove the access panel (on page 
). 
4. 
5. 
Install the storage controller ("
6. 
Connect the mini-SAS to mini-SAS cable, provided in the mini-SAS to mini-SAS cable option kit, to 
the hard drive backplane and to the storage controller. 
7. 
Install the air baffle. 
8. 
Install the access panel. 
9. 
Do one of the following: 
Close or install the tower bezel, as needed. 
Slide the server back into the rack. 
10. 
Power up the server (on page 
 
Battery-backed write cache battery pack option 
  
 
CAUTION:
  To prevent a server malfunction or damage to the equipment, do not add or 
remove the battery pack while an array capacity expansion, RAID level migration, or stripe 
size migration is in progress. 
  
  
 
CAUTION:
  After the server is powered down, wait 15 seconds and then check the amber LED 
before unplugging the cable from the cache module. If the amber LED blinks after 15 seconds, 
do not remove the cable from the cache module. The cache module is backing up data, and 
data is lost if the cable is detached.