1.  Getting Started 
This section is an overview of the steps required to commission an Aprisa SR radio network in the field: 
 
 
Phase 1:  Pre-installation 
 
1. 
Confirm path planning. 
Page  46 
2. 
Ensure that the site preparation is complete: 
 
Power requirements 
 
Tower requirements 
 
Environmental considerations, for example, temperature control 
 
Mounting space 
Page  49 
 
 
Phase 2:  Installing the radios 
 
1. 
Mount the radio. 
Page  52 
2. 
Connect earthing to the radio. 
Page  51 
3. 
Confirm that the: 
 
Antenna is mounted and visually aligned 
 
Feeder cable is connected to the antenna 
 
Feeder connections are tightened to recommended level 
 
Tower earthing is complete 
 
4. 
Install lightning protection. 
Page  51 
5. 
Connect  the  coaxial  jumper  cable  between  the  lightning  protection  and  the 
radio antenna port. 
Page  55 
6. 
Connect the power to the radio. 